August/September 2010
Wildish Construction Co.
was busy during the
month of June at the
Eugene
Airport. With crews
working around the
clock seven days a
week, 19,000 cubic
yards of material
were excavated,
33,000 tons of
aggregate and 56,300
tons of asphalt were
placed, and 53 storm
sewer manholes were
raised.
Wildish Sand &
Gravel Co. personnel
did a great job of
meeting the
construction
schedule with all of
the aggregate
products.
Company truck
drivers provided an
average of 35 trucks
per day, peaking at
61 when 8,700 tons
of shoulder rock
were placed.
While one crew
assisted with the
shoulder excavation
and rocking, another
crew assisted with
the manhole
adjustments.
All of this work had
to be completed
within the month of
June in order to
minimize disruption
to air traffic –
failure to meet the
deadline meant
liquidated damages
in the amount of
$2500 per
hour. Not
only was the job
completed on time,
Wildish crews worked
10,414 hours, and
subcontractors added
another 7,283
hours, without a
lost time injury.
Next on the work
schedule is a Lane
County
overlay project.
There are 6,800 tons
of shoulder rock to
place after the
paving crew puts
down 22,400 tons of
asphalt. This
project has a
completion date of
October 1.
Work at the intersection of US 20 and
Airport Road
in Lebanon is completed. The
concrete crew
finished the last of
the curb, gutter and
sidewalk, and the
paving crew
completed a two-inch
overlay in a busy
intersection.
Crews are now
working nights on
the I-5 Halsey to
Lane County Line job
preparing for this
mainline grind and
inlay project.
A crew has removed
earthen mounds,
replaced guardrail
flares, removed and
replaced concrete
barrier, and
micro-milled bridge
decks.
Paving crews have
been gearing up for
the paving operation
at the Diamond Hill
Interchange, both
rest areas at mile
post 206, and over
50 lane miles of I-5
northbound and
southbound lanes.
Approximately 87,000
tons of asphalt will
be placed in 30
shifts of paving.
Work on the LTD EmX
job is expected to
be completed by the
end of August.
At that time,
LTD will begin test
runs of busses on
the newly
constructed bus
lanes, wrapping up
this two season
effort.
Overlays of
Harlow
and Hayden Bridge
Roads and the
River Road
area streets are
nearing completion
as well, with all
main line paving
complete and only
manholes to and
driveways to finish.
Work begins in
mid-August on the
Albany
Airport project.
This $1.2 million
project includes
grinding and asphalt
overlay of the main
runway, as well as
new drainage and
electrical
improvements.
This job is
scheduled to be
complete by October.
In time for Duck
football season, the
new turf is in place
at Autzen Stadium.
Crews removed the
old turf, flattened
the crown, and
installed new
drainage in
preparation for the
new field surface.
The view and function of Pioneer Parkway in Springfield have been greatly improved thanks
to the efforts of
Wildish Building Co.
crews.
The addition
of new landscaping,
bus ways and art
sculptures greatly
enhance this
corridor which will
enable the EmX buses
to serve riders from
the Springfield
Station to the RiverBend Hospital
and Gateway Mall.
LTD will
begin testing the
route in August,
with use by the
public set for
January 1, 2011.
LTD recently awarded
a contract to the
company for
additional
renovation work at
the Springfield downtown
station.
These
modifications will
enable the new EmX
buses to efficiently
board passengers at
this station.
The work
includes
construction of a
new boarding area on
South A Street,
a new special event
boarding area, and
replacement of the
west boarding
platform.
This work is
underway and is
expected to be
complete by the end
of August.
The Hunt-Wildish JV
has concluded with
the installation of
the new field turf
at Autzen Stadium.
Remaining change
order work includes
new field wall
graphics around the
perimeter walls at
the field level, and
the installation of
new ESPN fiber optic
lines that enable
the television crew
to simply plug in at
the field level
instead of going up
and over the seating
bowl as previously
had to be done.
The Eugene Water and
Electric Board
recently awarded the
company a $500,000
contract for the
Carmen Smith
Communication
Building Project.
This work includes a
small electrical
communications
building and a new
50 foot radio tower.
This project has a
three month schedule
with tight site
logistics.
Three
projects have begun
at EWEB’s
Hayden Bridge water filtration plant in Springfield.
The first
project involves
installation of
about 400 feet of
six and eight inch
buried water main
through a maze of
existing pipes,
conduits and other
obstacles.
The second
project includes the
demolition of two
steel tanks, two
stainless steel
tanks and various
other items on the
second and third
floor of the
facility.
The third
project requires
construction of a
new 2,000 foot
access road through
a steep graded
forest.
All three
projects will be
completed in August.
Landscaping repairs
for the MWMC Peak
Flow project has
completed a major
hurdle with several
acres of irrigation
restored and fields
regraded and seeded.
In southern Oregon near Grants Pass, Wildish Standard Paving Co.’s
work on the historic
Rock Point Bridge
over the
Rogue River
is progressing
rapidly. Crews have
overcome a variety
of challenges to
meet the established
October 15
completion date.
All of the
new overhang,
ornamental dentils
and sidewalk
brackets, and
ornamental concrete
bridge rail have
been installed.
Using Fiber
Reinforced Polymer
(FBR) to strengthen
the 90 year old
concrete arch has
been similar to
putting a lot of
very stout fiber
“bandages” on the
concrete, then
covering them with
superglue.
When the
bridge closes to
traffic again after
Labor Day, crews
will place a
microsilica concrete
overlay on the deck,
remove temporary
access, and finish
the approach work at
the ends.
Moving north to the
Willamette Valley and the I-5 Vertical Clearance
job, crews have
raised seven of the
11 bridges. These
are the Talbot,
Dever-Conner,
Grand Prairie,
Seven Mile, Coleman,
MLK/Centennial and
Wilkins overpasses.
The MLK/Centennial
bridge was
interesting because
it is actually two
structures married
by a closure pour at
centerline (that is,
there is no joint
between the two).
One structure was
built in 1959 and
the other in 1972.
Crews are now
repairing
foundations, adding
to the embankments,
paving, and
replacing guard rail
to bring the road
approaches up to the
same elevation as
the raised bridges.
The overpasses at
Reed and I-105 west
bound are next in
line, with Egge and
Market following.
The most difficult
site appears to be
the I-105 structure
since this bridge
will be lifted a
total of 18 inches,
and will require
5,600 tons of
asphalt to raise the
road approaches. The
work will occur
during short night
time closures since
traffic must be
reopened every day.
Further north in
Portland,
both new bridges at
the Tualatin River project have been opened to
traffic. At
Stafford Road
site, traffic was
moved into a stage
alignment on the new
structure so the
existing bridge and
work bridge could be
removed.
Later this
fall, new fills,
including drainage
structures and water
quality ponds, will
be constructed, the
roadway will be
widened, and traffic
will be shifted into
its final
configuration.
At the Borland Road site, traffic is now using
the new bridge.
This allows
crews to remove the
detour bridge and
roadway alignment,
complete the tie-in
to the adjoining
roads, and install
water quality
structures and
ponds.
At the Oregon City
Arch Bridge
project, crews have
been getting the job
trailer and access
set for in-water
work. For the first
time in company
history, barges were
used to ship Wildish
equipment and
materials to the
project site. Crews
will start removing
debris from inside
the arch chamber
this summer,
building column
repair falsework,
and completing arch
investigation work.
The replacement of the bridge joints on the
Glenn
Jackson
Bridge
is more than halfway
done. Crews have
been working days,
nights and weekends
chipping out the old
bridge joints and
replacing them. The
north bound joints
are complete, so
work is now focused
on the south bound
joints. The
installation of
bridge joint seals,
placement of
concrete in the
existing wheel ruts,
final striping and
cleanup will occur
prior to the end of
October.
At Bonneville Dam,
crews have placed
approximately 4000
cubic yards of
concrete in the
hollow Ambursen
cells. They
plan to complete
excavations and
drain rock
placements soon, and
then place the
remaining 6000 cubic
yards of concrete to
complete this job.
Down the road at Cascade Locks, bridge crews have
finished removing
the detour
structure, assisted
in staining and
painting the
permanent
structures, and are
in the process of
cleanup and
demobilization.
Site crews completed
the detour fill
removal and are
working on reshaping
the fill to the
original contours.
They are also
completing swale and
pipe work along with
cleanup and punch
list activities.
Heading east on
I-84, work on the 15
Mile project is
moving at a rapid
pace with
construction of the
Stage 1 abutments
and center pier.
BT85 girders are
scheduled to be set
near the end of
August which will
allow crews to start
on the diaphragms,
deck and end panels.
They will soon be
starting retaining
wall modifications
in order to allow
the grading
subcontractor access
to rebuild a section
of I-84.
Crews are also
engaged in
construction of the
Bent 2 right footing
and lower column.
This work must be
done during the
in-water work window
and be completed
before the end of
October. The
demolition
subcontractor must
also add a few
footings and extra
beams to the
containment
structure so that it
is ready for Stage 2
demolition this
winter.
Across the Cascade Mountain Range,
construction on the
Harper Creek-to-Mule
Shoe Creek bridge
project started at
the end of June and
includes upgrades to
five bridges on
Highway 19 near
Spray.
The crew has
completed all of the
temporary access
platforms for
installation of the
Fiber Reinforced
Polymer (FRP) wrap
to strengthen the
existing bridge
beams.
Additionally,
they have completed
all of the structure
excavation at the
abutments (by
hand!), as well as
the core drilling
for rebar
installation for the
abutment
strengthening.
Existing
bridge rail and
guardrail flares
will be replaced in
the upcoming months.
Way out east, crews
at the Camas
and Dale Bridges
have completed
impacts, f-rail,
embankment, bridge
abutment backfill
and roadway base
rock in preparation
for August paving.
Demolition of the
existing piers at
both bridges is
finished, Camas
abutments are
completed for Stage
II, and the last
drilled shaft has
begun. The remaining
portions of the
substructure will be
completed in August.
At Coles Bridge,
the crew has removed
the diversions from
both sides of the
river, and is
installing the
riprap trench key
and abutment
protection. All pile
driving at this
bridge has been
completed, leaving
only portions of the
crossbeams and
bridge abutments to
be accomplished
before beams are
set.
At Goose Rock, the
crew has removed the
demolition
containment
structure, and river
diversions have been
installed for
removal of the
existing bridge
foundations. Both
abutments for Stage
II have been
completed, and crews
are focusing on
completing the
remaining in-water
work drilled shafts.
The Trout and
Silvies Slough
bridges will be
constructed during
August and
September. The
bridge at Trout
Creek is required to
be built in five
days, and the bridge
at Silvies Slough in
seven days. All
parts and pieces of
these bridges were
cast this spring and
are ready for
installation.